A former unpermitted landfill had lead-contaminated soil caused by battery cracking and disposal. Prior to treatment, TCLP levels were >5.0 mg/l lead. The client utilized pre-staged stockpiles and an excavator to apply EnviroBlend CS at a 3% dosage rate. Total cost savings of $1.75 million were realized by being able to dispose of the material in a non-hazardous Subtitle D landfill versus a hazardous Subtitle C landfill.

“EnviroBlend has always been a reliable product. We have successfully treated many tens of thousand tons of soil through the years.” – Confidential Client

Interested in more stories like this? Fill out the form below for a free download.

These case studies are examples of the extensive work EnviroBlend has completed across the United States. For more information on our project experience please contact us.