Conducted a time-critical removal action to clean up a site purchased as part of a residential relocation program. Provided construction management for in situ treatment and stabilization of 3,700 cu. yd. of soil impacted with lead from crushed batteries. Removed impacted soil to an off-site landfil and backfiled excavations with general fill. Completed the project within 1 month of authorization, and the client met the regulatory deadline.

Interested in more stories like this? Fill out the form below for a free download.