Conducted a time-critical removal action to clean up a site purchased as part of a residential relocation program. Provided construction management for in-situ treatment and stabilization of 3,700 cubic yards of soil impacted with lead from crushed batteries. Removed impacted soil to an off-site landfill and backfilled excavations with general fill. Completed the project within 1 month of authorization, and the client met the regulatory deadline.